The De Hart Field project has been
pushed back by as much as a year after the Township Committee voted to reject all three bidders for the project and put the
plan out for re-bid.
The move was done, in part, to end a lawsuit filed
by the lowest bidder, Andy Matt Inc., who was rejected after being considered unqualified.
TC member Jerry Ryan said Andy Matt agreed to withdraw its lawsuit if the project was re-bid, a move likely to occur
in early October. "We know all of the parties who will bid and we expect it to be much faster," Ryan said after
the meeting.
The lawsuit and a re-bid is yet another potential delay in
the project that was first voted down by voters last fall when it was for an artificial field. The newest plan, approved this
spring, is for a real grass field.
Andy Matt Inc. was the lowest of 11 bidders that submitted proposals last summer at $1.19 million, but was deemed
unqualified because it had not completed 10 previous similar projects
Turco
Golf, which offered the second-lowest bid at $1.275 million, was initially not awarded the contract because of questions about
their qualifications. But they received the contract after providing information on numerous past projects.
The project includes two overlapping soccer fields, a softball field, and other park improvements.
This plan, which will use a combination of grants and bonded funds, is for natural grass.
Andy Matt's lawsuit
asked that the Turco contract award be rejected and that the TC be ordered to award the contract to them. Instead, the TC
voted Tuesday, 5-0, to cancel the bidding and re-bid.
Ryan believed the
TC would be able to award the contract before the end of October. He said it would delay the project further, but did not
know by how much.
"It is not going to be done by the spring," he
said. "It is unlikely it will be done by the summer. The worst-case scenario has it by next fall."